Electric Consumer

Editor: Katerine G., Editor & Data Researcher · Research & publishing: Electric Consumer Editorial Team · Data retrieved · Sources named on this page: EIA-860/923 · How we got these numbers · Report an error

Power plants planned and retiring in Tennessee

3,340 MWTennessee planned power plant capacity

Tennessee plans 3,340 MW, 16% of its 21,163 MW in service (24th of 51). 1,036 MW is being built or tested; natural gas leads at 2,728 MW.

Tennessee: planned against running

Tennessee planned, by fuel

  • Solar 542 MW (16%)
  • Storage 70 MW (2%)
  • Natural gas 2,728 MW (82%)

Tennessee operating, by fuel

  • Solar 1,251 MW (6%)
  • Storage 1,616 MW (8%)
  • Natural gas 6,238 MW (29%)
  • Coal 4,704 MW (22%)
  • Nuclear 4,523 MW (21%)
  • Hydro 2,609 MW (12%)
  • Oil 136 MW (1%)
  • Other 87 MW (0%)

When Tennessee capacity arrives and leaves

MW due online and retiring in Tennessee, 2026 to 2034: 6 rows
YearTennessee planned MWTennessee retiring MW
202662No data
20271880703
202891710
2029720No data
2031No data1556
20346701675

6 rows from EIA-860M.

CSV

Tennessee projects dated after 2035 or without a year: 0 MW.

Where the Tennessee projects are

Tennessee counties with planned power plants, darker for more MWHardemanHaywoodCumberlandStewartRoaneMooreLakeHenryMadisonGibsonMonroeShelby

Tennessee: 12 counties shaded, darker for more planned MW.

Filter Tennessee planned projects

Filter the 14 planned project lines in Tennessee.

3,340 MW across 14 project lines, 16% of the 21,163 MW operating in Tennessee.

  • Kingston, Roane: 1,390 MW natural gas, online 2027
  • Cumberland (TN), Stewart: 670 MW natural gas, online 2029
  • Cumberland (TN), Stewart: 670 MW natural gas, online 2034
  • SR Tullahoma, Moore: 200 MW solar, online 2027
  • SR Copeland, Cumberland: 110 MW solar, online 2027

What the Tennessee numbers say

Tennessee runs 21,163 MW today. The planned list would add 3,340 MW (16%) while 5,644 MW (27%) of operating units carry a retirement date. Through 2035, Tennessee has 3,340 MW due online and 5,644 MW due to retire there.

Tennessee planned mix: 18% solar, storage and wind, 82% natural gas. Tennessee stages: 1,036 MW under construction or in testing, 195 MW permits received, not started, 2,109 MW early planning, no approvals started. Tennessee retired 1,577 MW from 2021 to 2026 and has 887 MW on the canceled or postponed list.

Tennessee capacity by fuel and status

Tennessee capacity by fuel
Tennessee fuelOperating MWPlanned MWRetiring MWRetired MWCanceled in Tennessee, MW
Solar1,251542––6
Storage1,61670–––
Wind–––29–
Natural gas6,2382,7281,051286881
Coal4,704–4,593865–
Nuclear4,523––––
Hydro2,609––––
Oil136––334–
Other87––63–
All fuels21,1633,3405,6441,577887

Tennessee counties with the most planned capacity

Tennessee counties by planned MW
Tennessee countyPlanned, MWGeneratorsLargest fuel
Roane County1,39018Natural gas
Stewart County1,3394Natural gas
Moore County2001Solar
Cumberland County1101Solar
Haywood County661Solar
Hardeman County551Solar
Henry County501Solar
Lake County501Storage
Madison County421Solar
Monroe County201Storage

Largest planned projects in Tennessee

Tennessee largest planned projects
Tennessee plantCountyFuelStageDueMW
KingstonRoaneNatural gasEarly planning, no approvals started20271,390
Cumberland (TN)StewartNatural gasEarly planning, no approvals started2029670
Cumberland (TN)StewartNatural gasUnder construction or in testing2034670
SR TullahomaMooreSolarUnder construction or in testing2027200
SR CopelandCumberlandSolarPermits received, not started2027110
SR DurhamvilleHaywoodSolarPermits received, not started202766
SR MiddletonHardemanSolarUnder construction or in testing202755
Ridgely Energy FarmLakeStorageEarly planning, no approvals started202950
SR PuryearHenrySolarUnder construction or in testing202750
SR DenmarkMadisonSolarUnder construction or in testing202642

Tennessee against its neighbors

Tennessee: planned MW equal 16% of operating. Bordering states: Alabama plans 6% of what it runs (10 points below Tennessee); Arkansas plans 35% of what it runs (19 points above Tennessee); Georgia plans 16% of what it runs (0 points above Tennessee); Kentucky plans 16% of what it runs (1 points above Tennessee); Missouri plans 16% of what it runs (1 points above Tennessee); Mississippi plans 26% of what it runs (10 points above Tennessee); North Carolina plans 6% of what it runs (10 points below Tennessee); Virginia plans 24% of what it runs (9 points above Tennessee).

Download

CSV by fuel CSV by project

Sources

EIA-860M inventory for Tennessee: 291 operating generators, 14 planned lines, edition August 2026, retrieved 5 Oct 2026. Sources for {e(sn)}.

More on Tennessee

Questions

Tennessee: how much new power plant capacity is planned?

3,340 MW, 16% of the 21,163 MW Tennessee runs. 1,036 MW is being built or tested in Tennessee.

Tennessee: what kind of power plants are planned?

Natural gas leads Tennessee with 2,728 of 3,340 planned MW.

Tennessee: which power plants are retiring?

5,644 MW of Tennessee units have a retirement date, of which 4,593 MW is coal and 1,051 MW natural gas.

Will Tennessee get all the planned plants?

Not necessarily. Tennessee has 887 MW canceled or postponed, and 1,577 MW (coal the largest group) retired from 2021 to 2026.

Share this page

3,340 MW Tennessee planned power plant capacity