In one sentence

The EIA-860M file lists every power plant unit that operates, is planned, has retired or was canceled; adding it up by state shows that 280,971 MW is planned in the 50 states and DC against 1,318,784 MW operating, with 73,169 MW set to retire.

What the status codes mean

How EIA planned-project status codes map to the stages on this site
Status code in the fileWhat it meansOur stage name
V, U, TSUnder construction (more or less than half complete) or construction complete, not yet in commercial operationUnder construction or in testing
TRegulatory approvals received, not under constructionPermits received, not started
LRegulatory approvals pending, not under constructionPermits pending
PPlanned, regulatory approvals not initiatedEarly planning, no approvals started

How we group fuels

Fuel groups used on the pipeline pages
Fuel group hereIncludes
SolarPhotovoltaic and solar thermal
StorageBatteries, pumped storage, flywheels and other storage
WindOnshore and offshore wind
Natural gasNatural gas and other gas generators
CoalBituminous, subbituminous, lignite, anthracite and waste coal
NuclearNuclear
HydroConventional hydroelectric
OilDistillate, residual, jet fuel, kerosene, petroleum coke and waste oil
OtherGeothermal, biomass, landfill gas, waste heat, hydrogen and anything else

Capacity and its limits

  • We use net summer capacity: what a unit can deliver at peak summer conditions, in MW. Nameplate capacity is higher for many units.
  • 65 operating units have no net summer figure in the file and count as zero.
  • The file lists capacity, not energy. A megawatt of solar or a battery produces or moves far fewer MWh than a megawatt of gas or nuclear, so capacity totals overstate the weight of solar and storage in the energy mix.
  • Planned means planned. The canceled-or-postponed list holds 174,768 MW today, but it is a running list of past projects, so it cannot be turned into a failure rate for the current pipeline.
  • Retirement dates are owners' current plans and move often.
  • Puerto Rico and the other territories are left out.

Sources and dates

Sources for the power plant pipeline with periods and dates
SourcePeriodRetrievedUsed for
EIA, Preliminary Monthly Electric Generator Inventory (EIA-860M)inventory as of August 2026: operating, planned, retired, canceled or postponed5 Oct 2026All capacity, status and year figures
U.S. Census Bureau, cartographic boundary files, counties 2023county outlinesas built on this siteCounty maps

Capacity is net summer capacity in MW. Planned does not mean built. How to read the inventory.

Questions

What is EIA-860M?

A monthly inventory of U.S. electric generators from the Energy Information Administration, listing operating, planned, retired and canceled units. It is preliminary: the annual EIA-860 survey is the final record.

What is net summer capacity?

The maximum output a unit can sustain at peak summer conditions, in megawatts, as reported to EIA.

Why are batteries counted as capacity?

EIA lists battery systems as generators with a power rating. Their energy storage in MWh is a different figure and is not used here.

Does a planned project always get built?

No. Projects slip, change fuel or are canceled.

Where can I get the numbers?

Every state and fuel total is in the CSV on the hub page, and every planned project is in a second CSV, both built from the August 2026 inventory.

Share this page

What the EIA-860M status codes mean, how we group fuels, why net summer capacity is used and what the planned list does not tell you.