Electric Consumer

Editor: Katerine G., Editor & Data Researcher · Research & publishing: Electric Consumer Editorial Team · Data retrieved · Sources named on this page: EIA-860/923 · How we got these numbers · Report an error

Power plants planned and retiring in New Jersey

35 MWNew Jersey planned power plant capacity

New Jersey plans 35 MW, 0% of its 16,757 MW in service (50th of 51). 33 MW is being built or tested; solar leads at 21 MW.

New Jersey: planned against running

New Jersey planned, by fuel

  • Solar 21 MW (62%)
  • Storage 13 MW (38%)

New Jersey operating, by fuel

  • Solar 1,296 MW (8%)
  • Storage 548 MW (3%)
  • Wind 8 MW (0%)
  • Natural gas 11,164 MW (67%)
  • Nuclear 3,459 MW (21%)
  • Hydro 12 MW (0%)
  • Oil 85 MW (1%)
  • Other 186 MW (1%)

When New Jersey capacity arrives and leaves

MW due online and retiring in New Jersey, 2026 to 2035: 7 rows
YearNew Jersey planned MWNew Jersey retiring MW
2026331
20271178
2028No data9
2030No data10
2031No data14
2032No data4
2035No data28

7 rows from EIA-860M.

CSV

New Jersey projects dated after 2035 or without a year: 0 MW.

Where the New Jersey projects are

New Jersey counties with planned power plants, darker for more MWAtlanticUnionSalemSomersetMiddlesexSussexMercer

New Jersey: 7 counties shaded, darker for more planned MW.

Filter New Jersey planned projects

Filter the 10 planned project lines in New Jersey.

35 MW across 10 project lines, 0% of the 16,757 MW operating in New Jersey.

  • Milltown Onsite BESS, Middlesex: 13 MW storage, online 2026
  • Hamms Landfill, Sussex: 6 MW solar, online 2026
  • Prologis - SLCNJ001 - Community Solar, Middlesex: 3 MW solar, online 2026
  • Carneys Point Solar 1 LLC, Salem: 3 MW solar, online 2026
  • Harrah's Atlantic City - POI 1 (Meeting, Atlantic: 2 MW solar, online 2026

What the New Jersey numbers say

New Jersey runs 16,757 MW today. The planned list would add 35 MW (0%) while 280 MW (2%) of operating units carry a retirement date. Through 2035, New Jersey has 35 MW due online and 244 MW due to retire there.

New Jersey planned mix: 100% solar, storage and wind, 0% natural gas. New Jersey stages: 33 MW under construction or in testing, 1 MW permits received, not started. New Jersey retired 1,512 MW from 2021 to 2026 and has 4,384 MW on the canceled or postponed list.

New Jersey capacity by fuel and status

New Jersey capacity by fuel
New Jersey fuelOperating MWPlanned MWRetiring MWRetired MWCanceled in New Jersey, MW
Solar1,296211041020
Storage548132–8
Wind8–––2,363
Natural gas11,164–1749961,993
Coal–––463–
Nuclear3,459––––
Hydro12––––
Oil85––23–
Other186––19–
All fuels16,757352801,5124,384

New Jersey counties with the most planned capacity

New Jersey counties by planned MW
New Jersey countyPlanned, MWGeneratorsLargest fuel
Middlesex County162Storage
Sussex County61Solar
Somerset County32Solar
Salem County31Solar
Atlantic County21Solar
Union County22Solar
Mercer County11Solar

Largest planned projects in New Jersey

New Jersey largest planned projects
New Jersey plantCountyFuelStageDueMW
Milltown Onsite BESSMiddlesexStorageUnder construction or in testing202613
Hamms LandfillSussexSolarUnder construction or in testing20266
Prologis - SLCNJ001 - Community SolarMiddlesexSolarUnder construction or in testing20263
Carneys Point Solar 1 LLCSalemSolarUnder construction or in testing20263
Harrah's Atlantic City - POI 1 (MeetingAtlanticSolarUnder construction or in testing20262
BPL NJ - BelmontSomersetSolarUnder construction or in testing20262
50 Meister AveSomersetSolarUnder construction or in testing20262
East Windsor Solar 1 LLCMercerSolarPermits received, not started20271
Elizabeth Metropolitan Logistics CenterUnionSolarUnder construction or in testing20261
BPL NJ - Union Distribution CenterUnionSolarUnder construction or in testing20261

New Jersey against its neighbors

New Jersey: planned MW equal 0% of operating. Bordering states: Delaware plans 7% of what it runs (7 points above New Jersey); New York plans 17% of what it runs (17 points above New Jersey); Pennsylvania plans 13% of what it runs (13 points above New Jersey).

Download

CSV by fuel CSV by project

Sources

EIA-860M inventory for New Jersey: 633 operating generators, 10 planned lines, edition August 2026, retrieved 5 Oct 2026. Sources for {e(sn)}.

More on New Jersey

Questions

New Jersey: how much new power plant capacity is planned?

35 MW, 0% of the 16,757 MW New Jersey runs. 33 MW is being built or tested in New Jersey.

New Jersey: what kind of power plants are planned?

Solar leads New Jersey with 21 of 35 planned MW.

New Jersey: which power plants are retiring?

280 MW of New Jersey units have a retirement date, of which 0 MW is coal and 174 MW natural gas.

Will New Jersey get all the planned plants?

Not necessarily. New Jersey has 4,384 MW canceled or postponed, and 1,512 MW (natural gas the largest group) retired from 2021 to 2026.

Share this page

35 MW New Jersey planned power plant capacity